EAO issues Section 11 order for Raven project review

Rachel Shaw, Project Assessment Mgr, Environmental Assessment Office, March 5, 2010

Section 11 Order for the Raven Underground Coal Project

An order issued under Section 11 of the Environmental Assessment Act establishes the scope and procedures concerning the environmental assessment of the proposed project. In reading the Section 11 order, note particularly its structure, and the sections noted below.

While the project review is in Pre-Application Stage

- 3. Scope of the Proposed Project

- 4. Scope of the Assessment

- 9. Application Information Requirements

- 11. Public Consultation

Sections 13 and following are mainly concerned with the project and its review once the Application is filed and the review enters its Assessment Stage